Conflict Affected Region Emergency Project: Lot A Construction of 132/33kV Grid Substation at Chunnakam
Client :
Ceylon Electricity Board /Siemens (India)
Overview :
Construction of 132/33kV Substation including construction of control building, two transformer foundations, outdoor switch yard foundation, fencing gates, guard houses etc.
Status :
To be complete in 2013
Power Sector Development Transmission Project Lot A - Anniyakanda Grid Substation
Client :
Ceylon Electricity Board /Siemens AG (Austria)
Overview :
This project covered construction of control building, two transformer foundations including fire walls, outdoor switchyard foundations, fencing, gates, guard house, watch tower, water tower and engineers office, internal roads, water supply and drainage systems on full turn key basis.
Status :
Completed in 2008
Power Sector Development Transmission Project - Lot A Bolawatta - Grid Substation
Client :
Ceylon Electricity Board /Siemens AG (Austria)
Overview :
This project covered construction of control building, outdoor switchyard foundation, fencing, gates, internal roads, water supply and drainage systems.
Status :
Completed in 2009
Power Sector Development Transmission Project - Lot A Katunayake - Grid Substation
Client :
Ceylon Electricity Board /Siemens AG (Austria)
Overview :
This project covered construction of control building, two transformer foundations including fire walls, outdoor switchyard foundations, fencing, gates, guard house, watch tower, water tower, engineers office, internal roads, water supply and drainage systems on full turn key basis.
Status :
Completed in 2010
Colombo City Electricity Distribution Development Project Substation C (GIS) - Kotahena
Client :
Ceylon Electricity Board/ABB AG (Germany)
Overview :
This project involved the constructions of two no. of 31.5MVA transformer foundations, current & auxiliary transformers, security fence & gates, three storeyed GIS control building and related road developments.
Status :
Completed in 2011