Construction of Concrete Pad & Chimney Foundations and Pile Foundation for Towers of 132kV Double Circuit Transmission Line (Rantambe to Mahiyanganaya Grid Substation) - Package A

Client :

Ceylon Electricity Board

Overview :

This project involved survey checks, excavation, shoring, de-watering, stub settings, concreting & backfilling of tower foundations, supply & driving of piles, construction of pile caps and capping beams.

Status :

Completed in 2011

Erection of Towers Section A of 132kV Double Circuit Transmission Line from Rantambe Grid Substation to Mahiyanganaya Grid Substation - Package A & B

Client :

Ceylon Electricity Board

Overview :

This project has been implemented to cover all tower erection work

Status :

To be completed in 2012